Question: Samson Building, Ltd., is also constructing an identical building for the same funder as in Exercise 6 and has the following EVs and costs for
Samson Building, Ltd., is also constructing an identical building for the same funder as in Exercise 6 and has the following EVs and costs for the first 6 days: EV: 90, 88, 95, 101, 89, 105; Cost: 92, 88, 93, 98, 85, 100. Compare this project to the two in Exercise 6.