The project manager is creating an estimate for building a warehouse and distribution center. It is a
Question:
The project manager is creating an estimate for building a warehouse and distribution center. It is a project similar to those he executes about three times a year. He is using the rule of thumb of $100 per square foot to calculate the estimate. What type of estimate is this?
a. Parametric
c. Gut feel
b. Analogous
d. Bottom-up