Question: The project manager is creating an estimate for building a warehouse and distribution center. It is a project similar to those he executes about three
The project manager is creating an estimate for building a warehouse and distribution center. It is a project similar to those he executes about three times a year. He is using the rule of thumb of $100 per square foot to calculate the estimate. What type of estimate is this?
a. Parametric
c. Gut feel
b. Analogous
d. Bottom-up
Step by Step Solution
3.46 Rating (159 Votes )
There are 3 Steps involved in it
The type of estimate the project manager is using in this scenario is b Analogous Heres why the othe... View full answer