Question: The project manager is creating an estimate for building a warehouse and distribution center. It is a project similar to those he executes about three

The project manager is creating an estimate for building a warehouse and distribution center. It is a project similar to those he executes about three times a year. He is using the rule of thumb of $100 per square foot to calculate the estimate. What type of estimate is this?

a. Parametric 

c. Gut feel

b. Analogous 

d. Bottom-up

Step by Step Solution

3.46 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The type of estimate the project manager is using in this scenario is b Analogous Heres why the othe... View full answer