Question: Two project activities A and B (B being dependent on A) have a finishfinish relationship with 8 days lag. The estimated durations for the activities
Two project activities ‘A’ and ‘B’ (B being dependent on A) have a finish–finish relationship with 8 days ‘lag’. The estimated durations for the activities are 10 days and 15 days, respectively. If activity ‘A’ is scheduled to start on the 12th day from the beginning of project, on which day can you schedule to start activity ‘B’?