Question: Two project managers are looking for the same resource to perform work on their projects. In one project, the work is on a task on
Two project managers are looking for the same resource to perform work on their projects. In one project, the work is on a task on a feeding path, in which the feeding buffer is 95 percent consumed. In the other project, the work is on the Critical Chain, in which the Critical Chain is 50 percent complete and the project buffer is 0 percent consumed. Which task should the resource be assigned to first? Why?
Step by Step Solution
3.42 Rating (155 Votes )
There are 3 Steps involved in it
In the context of Critical Chain project management the feeding path refers to noncritical tasks tha... View full answer