Question: You are a project manager for a medium-sized charitable organization. You are required to plan an outdoor fundraiser that needs to be publicized, with the
You are a project manager for a medium-sized charitable organization. You are required to plan an outdoor fundraiser that needs to be publicized, with the target of attracting 300 people to the event.
a. Create a table to illustrate the activities associated with delivering this project and identifying which tasks have predecessors.
b. Draw the activity diagram, illustrating burst and merge activities.