You have a partial network for your project, and you are about to conduct a forward pass

Question:

You have a partial network for your project, and you are about to conduct a forward pass through it. Explain why the early start (ES) for activity G is 23 days, not 19 days.

Remember, activity G is a merge activity.image text in transcribed