Question: For the reference, posting the 9.12 question Please answer 9.13 Question 9.13 Referring to the figure in Problem 9.12 g, suppose that Activity G was

For the reference, posting the 9.12 question

Please answer 9.13 Question
9.13 Referring to the figure in Problem 9.12 g, suppose that Activity G was the last activity in the network and you were about to start a backward pass. a. What is the project's duration? (Hint: complete the forward pass) b. What are the late finish (LF) and late start (LS) values for activities E, F, and G? c. Which activity has slack time? How many days? 9.12 You have a partial network for your project, and you are about to conduct a forward pass through it. Explain why the early start (ES) for activity G is 23 days, not 19 days. Remember, activity G is a merge activity. 16 E 23 7 G 4 14 F 19 5Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
