Your customer has requested a minor change to the project that shouldnt impact the schedule. How should

Question:

Your customer has requested a minor change to the project that “shouldn’t impact the schedule.” How should you respond?

a. Authorize the change to maintain good customer relations

b. Refuse the change because you wish to avoid scope creep

c. Evaluate the impact of the change against the other project constraints.

d. Involve top management to determine the best course of action