Question: A project deliverable is often developed by multiple organizational units. Which WBS element can be used to assign work responsibilities to organizational units? A. Control
A project deliverable is often developed by multiple organizational units.
Which WBS element can be used to assign work responsibilities to organizational units?
A. Control accounts B. Organizational breakdown structure (OBS)
C. Responsibility assignment matrix (RAM)
D. Work packages