Question: A project has the following performance data: AC = 2,000,000 CV = 250,000 SPI = 1.12 BAC = 10,000,000 What is

A project has the following performance data:

• AC = 2,000,000

• CV = –250,000

• SPI = 1.12

• BAC = 10,000,000 What is the project earned value?

A. 1,750,000 B. 1,562,500 C. 2,250,000 D. There is not enough information.