Question: A project has the following performance data: AC = 2,000,000 CV = 250,000 SPI = 1.12 BAC = 10,000,000 What is
A project has the following performance data:
• AC = 2,000,000
• CV = –250,000
• SPI = 1.12
• BAC = 10,000,000 What is the project earned value?
A. 1,750,000 B. 1,562,500 C. 2,250,000 D. There is not enough information.