Question: A project is being completed by a virtual team with team members from six countries. From their various locations, the team members are arguing about
A project is being completed by a virtual team with team members from six countries. From their various locations, the team members are arguing about which office will take the lead on the project, disagreeing over meeting schedules, and questioning the abilities of individuals whom they have not worked with before. In which stage of the Tuckman ladder is this team functioning? A. Forming B. Reforming C. Storming D. Resourcing