Question: A project manager is in the process of developing the stakeholder register. He creates a list of potential stakeholders and decides to use a datagathering
A project manager is in the process of developing the stakeholder register.
He creates a list of potential stakeholders and decides to use a datagathering technique to share a list of questions with the individual participants before the group creativity session.
What technique did the project manager apply in the given scenario?
A. Brainstorming B. Questionnaires and surveys C. Brainwriting D. Stakeholder mapping