Question: A project manager is informed midway through project planning that she was given inaccurate data regarding new regulations affecting the required end date of her
A project manager is informed midway through project planning that she was given inaccurate data regarding new regulations affecting the required end date of her project. She may need to make a few adjustments, but she thinks she can still manage the project to complete it before the regulations take effect. She confirms this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?
A. Critical path method B. Flowchart C. Precedence diagramming D. Work breakdown structure