Question: A project manager may use _______ to make sure the team members clearly know what is included in each of their work packages. A. The
A project manager may use _______ to make sure the team members clearly know what is included in each of their work packages.
A. The project scope statement B. The product scope C. The WBS dictionary D. The schedule