Question: A project team is creating a project management plan when management asks them to identify project risks and provide some form of qualitative output as
A project team is creating a project management plan when management asks them to identify project risks and provide some form of qualitative output as soon as possible. What should the project team provide? A. Risk triggers B. Prioritized list of risks C. Contingency reserves D. Probability of achieving the time and cost objectives