Question: Accepting a risk is a reasonable response strategy when: A. There is not enough information to accurately analyze the risk B. The risk has never

Accepting a risk is a reasonable response strategy when:

A. There is not enough information to accurately analyze the risk B. The risk has never occurred before in the organization C. There are no workarounds available D. It is not possible to transfer, mitigate, or avoid the risk