Question: According to PMI, the main Inputs to the Develop Project Charter Process are the following: A) Business Case, Benefits Management Plan, Any earlier, but relevant
According to PMI, the main Inputs to the “Develop Project Charter” Process are the following:
A) Business Case, Benefits Management Plan, Any earlier, but relevant Contracts and Agreements, EEFs, and OPAFs.
B) Expert judgment, Data gathering approaches, Interpersonal and team skills, Meetings.
C) Business Case, Benefits Management Plan, Assumption Log, and EEFs and OPAFs.
D) All Options above are Correct.
ANSWER: A
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts