Question: Adam is a project manager of a complex cloud integration project. The project is in the planning stage and needs three DevOps expert consultants, who

Adam is a project manager of a complex cloud integration project. The project is in the planning stage and needs three DevOps expert consultants, who are unavailable internally. After reviewing the preferred supplier list with the procurement manager, Adam decides to hold a bidder conference with three prospective sellers.

What type of contract is most suitable in the scenario stated above?

A. Fixed Price with economic price adjustments (FP-EPA) B. Cost Plus Incentive Fee (CPIF) C. Time and Material (T&M) D. Cost Plus Award Fee

(CPAF)