Question: After completing the WBS, the activity list, and the network diagram, the project manager estimated activity durations. What has he done wrong? A. Forgot to
After completing the WBS, the activity list, and the network diagram, the project manager estimated activity durations. What has he done wrong?
A. Forgot to level the resources B. Did not optimize the project schedule C. Did not involve the project team D. Forgot to analyze the overall schedule risk
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
