Question: After completing the WBS, the activity list, and the network diagram, the project manager estimated activity durations. What has he done wrong? A. Forgot to

After completing the WBS, the activity list, and the network diagram, the project manager estimated activity durations. What has he done wrong?

A. Forgot to level the resources B. Did not optimize the project schedule C. Did not involve the project team D. Forgot to analyze the overall schedule risk