Question: An important stakeholder complained that he is receiving too much technical documentation and no performance reports. Which process could have avoided this problem? A. Identify

An important stakeholder complained that he is receiving too much technical documentation and no performance reports. Which process could have avoided this problem?

A. Identify stakeholders B. Identify risks C. Report performance D. Plan communications management