Question: An organization that typically operates as a weak matrix has decided that for a high-priority project, the team will work on the project full time.
An organization that typically operates as a weak matrix has decided that for a high-priority project, the team will work on the project full time. In addition, the project manager will manage just this one project full time. What type of organization structure is this?
A. Simple B. Project-oriented C. Strong matrix D. Hybrid