Question: As the project manager for the DFK Project, you are reviewing your project's network diagram (as shown in the following illustration): Given the diagram, what
As the project manager for the DFK Project, you are reviewing your project's network diagram (as shown in the following illustration):
Given the diagram, what is the relationship between tasks F and G?
A.
FS B.
SS C.
FF D.
SF
Sart ES EF3 E5-4 B ES ES-10 2 E ES-12 1-13 G EF-15 ES-14 17-20 LS=14 LF-20 End