Question: During the middle of a software development project that uses AgileScrum methodology, the Scrum Master leaves the company. This event was documented as a risk

During the middle of a software development project that uses AgileScrum methodology, the Scrum Master leaves the company. This event was documented as a risk during the initiation phase of the project.

What corrective action needs to be taken in the abovementioned situation?

A. Ask the product owner to play a dual role.

B. Ask the seniormost team member to play the role of Scrum Master. C.

Examine the assumption log and take appropriate action. D. Review the project charter and work with the functional manager to resolve the issue.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!