Question: Given below are the network data and the timetost trade-off data for a small maintenance project. Table 8-2 Predecessor Normal Job (Activity) Jobs (days) (dollars)
Given below are the network data and the timetost trade-off data for a small maintenance project.

Table 8-2 Predecessor Normal Job (Activity) Jobs (days) (dollars) Crash (days) ABCDEFG none none none A Total 140 50 100 55 A 7 115 B, D 100 610 3625274 50 2413252 Cost Slope (dollars/day) 50 60 30 40 30 70