Question: How does a risk reassessment differ from a risk audit? A. A risk audit is conducted only at the end of the project. B. A
How does a risk reassessment differ from a risk audit?
A. A risk audit is conducted only at the end of the project.
B. A risk reassessment is focused on the overall project risk, while a risk audit is focused on the individual risk.
C. A risk reassessment is focused on individual risks, while the risk audit is focused on the risk management process.
D. A risk reassessment is normally conducted by an external team, while a risk audit is conducted by team members.