Question: If you are compressing the project schedule by using a technique that generally does not increase project costs, which of the following techniques are you
If you are compressing the project schedule by using a technique that generally does not increase project costs, which of the following techniques are you using?
A. Fast tracking B. Crashing C. Resource optimization D. Resource leveling