Question: In a two-year project, the project manager has intentionally delayed a solution design activity. The project manager and the team are expecting that in the
In a two-year project, the project manager has intentionally delayed a solution design activity. The project manager and the team are expecting that in the next few months, a new and more effective technology might be available on the market. This is an example of:
A. Enhance risk B. Contingency plan C. Mitigate risk D. Exploit risk