Question: In which process does the project manager aggregate the estimated costs of individual activities in order to establish a cost baseline? A. Plan Cost Management
In which process does the project manager aggregate the estimated costs of individual activities in order to establish a cost baseline?
A. Plan Cost Management B. Estimate Costs C. Determine Budget D. Control Costs