Question: Key resources left the project without the project managers knowledge. Which of the following is the LEAST likely reason? A. Lack of a staffing management
Key resources left the project without the project manager’s knowledge.
Which of the following is the LEAST likely reason?
A. Lack of a staffing management plan B. Lack of a communications management plan C. Lack of a recognition and rewards systems D. Changes on resource allocation have not been validated by the functional manager