Question: One month before the projects scheduled completion, the customer requested an additional critical requirement. What should the project manager do NEXT? A. Request management support.
One month before the project’s scheduled completion, the customer requested an additional critical requirement. What should the project manager do NEXT?
A. Request management support.
B. Inform the customer that the requirement will be delivered by a future project.
C. Approve a change request before working on the new requirement.
D. Initiate integrated change control.