Question: Recall actual cost (AC), planned value (PV), earned value (EV), and cost variance (CV) in the earned value technique. The CV is calculated as: A.

Recall actual cost (AC), planned value (PV), earned value (EV), and cost variance

(CV) in the earned value technique. The CV is calculated as:

A. PV – EV B. AC – EV C. EV – AC D. PV – AC