Question: Riley is a new software development project manager who joined during the execution. He is trying to determine whether the modification of any of the

Riley is a new software development project manager who joined during the execution. He is trying to determine whether the modification of any of the project documents is subject to the change request.

What does the project manager need to review to fetch this information?

A. Review the Change Management Plan B. Refer to the Scope Management Plan C. Review the Configuration Management Plan D.

Examine Requirement Traceability Matrix