Question: Riley is a project manager of a complex engineering project. He and all risk owners have just completed an important risk management process and updated

Riley is a project manager of a complex engineering project. He and all risk owners have just completed an important risk management process and updated the risk register with information on agreedupon risk response strategies, triggers, warning signs of risk occurrence, and residual risks that are expected to remain because they are deliberately accepted. What risk management process has been concluded in the given scenario? A. Plan risk responses B. Perform qualitative risk analysis C. Identify risks D. Monitor risks