Question: Riley is a project manager of a software development project running behind schedule with the CPI - 1.3. The project manager decides to bring the

Riley is a project manager of a software development project running behind schedule with the CPI - 1.3. The project manager decides to bring the project back on track by applying the crashing technique.

What will happen to the project?

A. Costs and risks will increase.

B. Risks will increase.

C. Activities will be performed in parallel. D. The scope will be reduced.