Question: Riley is a project manager of an invoice processing project. He has identified eight important stakeholders for the project. The number of communication channels on
Riley is a project manager of an invoice processing project. He has identified eight important stakeholders for the project. The number of communication channels on this project is:
A. 9 B. 72 C. 36 D. 28