Question: Serious errors were found in the product during a test cycle in a software development project. Management is worried because the project CPI is 0.8

Serious errors were found in the product during a test cycle in a software development project. Management is worried because the project CPI is 0.8 and the SPI is 0.75. Additionally, the project is struggling with a lack of resources. Which of the following is the MOST likely cause?

A. Poor scope definition B. Inadequate quality management planning C. Lack of a staffing management plan D. Unidentified risks