Question: Task A is worth $200, is 100 percent complete, and actually cost $200. Task B is worth $75, is 90 percent complete, and actually cost

Task A is worth $200, is 100 percent complete, and actually cost

$200. Task B is worth $75, is 90 percent complete, and actually cost $120 so far. Task C is worth $200, is 75 percent complete, and has cost $175 so far. The total budget is $1,000. What is the Cost Variance for the tasks listed?

a. 0.

84

b. 0.88

c. −$77.50

d. −$57.50