Question: The integrated change control process is used to manage changes to the project at which stage? A. From initiating through closing B. Planning only C.
The integrated change control process is used to manage changes to the project at which stage?
A. From initiating through closing B. Planning only C. Executing only D. Monitoring and controlling only