Question: The main Inputs to the Conduct Daily Standup Process include the following: A) Inputs from the SCRUM Team, the SCRUM Master, and the Product Owner.

The main Inputs to the “Conduct Daily Standup” Process include the following:

A) Inputs from the SCRUM Team, the SCRUM Master, and the Product Owner.

B) The Sprint Burndown Chart, the Impediment Log Document, the Scrumboard, and the Inter-Tasks Dependencies.

C) Both Options above are Correct.

D) All Options above are Incorrect.

ANSWER: C