Question: The main Inputs to the Conduct Daily Standup Process include the following: A) Inputs from the SCRUM Team, the SCRUM Master, and the Product Owner.
The main Inputs to the “Conduct Daily Standup” Process include the following:
A) Inputs from the SCRUM Team, the SCRUM Master, and the Product Owner.
B) The Sprint Burndown Chart, the Impediment Log Document, the Scrumboard, and the Inter-Tasks Dependencies.
C) Both Options above are Correct.
D) All Options above are Incorrect.
ANSWER: C