Question: The main Inputs to the Perform Quantitative Risk Analysis Process are the Risk Management Plan, the Scope Baseline, the Schedule Baseline, the Cost Baseline, the

The main Inputs to the “Perform Quantitative Risk Analysis” Process are the Risk Management Plan, the Scope Baseline, the Schedule Baseline, the Cost Baseline, the Assumption Log, the Basis of Estimates, the Cost Estimates, the Cost Forecasts, the Duration Estimates, the Milestone List, the Resource Requirements, the Risk Register, and the Schedule Forecasts.

A) _TRUE_ B) _FALSE_ ANSWER: A