Question: The main Outputs of the Create Project Vision Process include the following: A) The identified Product Owner. B) The Project Vision Statement, the Project Charter,
The main Outputs of the “Create Project Vision” Process include the following:
A) The identified Product Owner.
B) The Project Vision Statement, the Project Charter, and the Project Budget.
C) Both Options above are Correct.
D) All Options above are Incorrect.
ANSWER: D
Step by Step Solution
There are 3 Steps involved in it