Question: The original plan for the project was for it to last one year at a cost of $100,000. Using the following information, calculate SPI, ETC,
The original plan for the project was for it to last one year at a cost of $100,000. Using the following information, calculate SPI, ETC, and EAC:
Planned value = $45,000 Earned value = $37,000 Cost variance = -$12,000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts