Question: The Outputs of the Develop Project Management Plan Process include a set of Subsidiary Project Baseline Documents such as a Scope Baseline, Schedule Baseline, Cost
The Outputs of the “Develop Project Management Plan” Process include a set of Subsidiary Project Baseline Documents such as a Scope Baseline, Schedule Baseline, Cost Baseline, and Performance Measurement Baseline.
A) _TRUE_ B) _FALSE_ ANSWER: A