Question: The plan risk responses process includes: A. Developing contingency plans and identifying the responses triggers B. Preparing a risk breakdown structure C. Determining risk causes
The plan risk responses process includes:
A. Developing contingency plans and identifying the responses’ triggers B. Preparing a risk breakdown structure C. Determining risk causes D. Prioritizing risks