Question: The Project Documents updated during the Identify Risks Process are the Assumption Log, the Issue Log, and the Lessons Learned Register. A) _TRUE_ B) _FALSE_

The Project Documents updated during the “Identify Risks” Process are the Assumption Log, the Issue Log, and the Lessons Learned Register.

A) _TRUE_ B) _FALSE_ ANSWER: A