Question: The project manager realized that functionality was informally added to the product scope. What is the FIRST thing to do? A. Evaluate the impact of
The project manager realized that functionality was informally added to the product scope. What is the FIRST thing to do?
A. Evaluate the impact of the added functionality.
B. Review the change control system to prevent further scope creep.
C. Find out how the functionality was added.
D. Prepare a change request, and ask the customer to approve it.