Question: The software development project has progressed according to plan. The team is very enthusiastic about the product they have created. Now they are looking ahead
The software development project has progressed according to plan. The team is very enthusiastic about the product they have created. Now they are looking ahead to finding new projects to work on. You caution them that the current project cannot be considered complete until after the closing process group. Closure includes all the following except: A. Determining performance measures B. Turning over the product of the project C. Documenting the degree to which each project phase was properly closed after its completion D. Updating the company's organizational process assets