Question: The team is going through some resource overutilization issues on the project. The database administrators are working excessive hours. The Project Manager has gone back

The team is going through some resource overutilization issues on the project. The database administrators are working excessive hours. The Project Manager has gone back to planning to reevaluate the situation. Which of the following can provide help in seeing how serious the issue is?

a. Pareto diagram

b. Control chart

c. Staffing Management Plan

d. Resource Histogram