Question: Two weeks before the project scheduled finish date, one team member informs you that a key stakeholder is not happy and is requesting a product

Two weeks before the project scheduled finish date, one team member informs you that a key stakeholder is not happy and is requesting a product change. What should you do FIRST?

A. Issue a change request.

B. Meet with the key stakeholder.

C. Finish the project before discussing future product improvements.

D. Analyze the impact of the change.