Question: Update the network given in Figure 4-6 based on the following activity progress report submitted at the end of the fifth working day. Activity Start

Update the network given in Figure 4-6 based on the following activity progress report submitted at the end of the fifth working day.

Activity Start Time Finish Tim Modifications 0-1 1 3 - 1-2 5 - -

0-3 0 2 - 3-4 3 - - 3-7 2 - - 0-6 5 - - 5-8 - - Activity duration estimate increased to four days for 5-8.

a. What is the current status of this project with respect to a scheduled completion time of 15 days?

b. What activities must be expedited to alleviate the situation found in (a)?